CEO Reviews Mega Projects: NSIT City Gate, Celestia Facade Progress

Date: Published 13 October 2026. Review held on a Saturday in August 2026.

Chief Executive Officer Imran Amin conducted a comprehensive inspection of several ongoing mega projects on a Saturday in August 2026, accompanied by Executive Director Technical Riaz Hussain, project management and construction directors, NESPAK officials and contractor representatives.

At CBD Vertex, finishing works were reported to be progressing rapidly, with exterior elevation tiles and digital screens nearing completion, and epoxy flooring plus an advanced parking management system in final stages. At CBD Walk, the grey structures of all units were complete with elevation tile installation progressing swiftly.

At NSIT City, the main structure of the central entrance gate was complete, the entrance passage nearing its final stage, and facade work on the multi-storey Celestia IT and Office Tower progressing rapidly. The entrance gate’s completion is a visible placemaking milestone for the authority’s largest district.

Following the inspections, the CEO chaired a progress review meeting on timelines, structural integrity and architectural standards, directing officers, consultants and contractors to complete the projects within stipulated timelines while maintaining construction quality.

The review confirms parallel finishing-stage progress across three fronts: commercial work at Vertex and the Walk, and the IT city at the NSIT City gate and Celestia. The stipulated completion dates themselves were not published in the report, so the milestones should be read as confirmed progress rather than a delivery schedule.

The review covered the authority’s three main fronts at once: commercial finishing at CBD Vertex and CBD Walk, and the IT city at NSIT City. CBD Vertex is a commercial development whose finishing works, including exterior elevation tiles, digital screens, epoxy flooring and an advanced parking management system, were reported to be in their final stages. At NSIT City, the central entrance gate’s main structure was complete and the entrance passage was nearing its final stage, while facade work on the Celestia IT and Office Tower was progressing rapidly. The same gate and tower were reviewed again by the chief executive in October 2026, when the Celestia tower’s final slab was reported complete and the gate’s core structural work finished.

Source: Business Recorder, August 2026.